Construction update from Hennessey Engineers:

1.)  East side McCann Ave driveway approach paving was completed Wednesday, July 10th.  We anticipate the new concrete driveway approaches will reach cure time next Wednesday, July 17th.

2.)  The contractor should complete pavement removal of the west side of McCann Ave next Monday, July 15th.

3.)  The contractor will begin grade cutting next Monday, July 15th. Concurrent with this work, edgedrain installation, drainage structures adjustments, gravel base placement and pavement forms will also be installed.  This work should be finished next Friday, July 19th.

4.)  It is anticipated paving of the west side of McCann Ave will take place the week of July 22nd.

5.)  High school parking lots are still available for resident parking.  Residents must access these parking lots from Leroy Ave.

6.)  Handicap access is maintained and will be adjusted as necessary during road construction.

7.)  Notices to update the residents will be hand delivered again tomorrow, Friday, July 12th.

The above outline is weather dependent.